1. FOUNDATIONS
5. SECONDARY CONCRETE FLOORPLATE


2. CONCRETE PILLARS INSTALLED

6. SECOND LEVEL OF MODULES INSTALLED
9. SAFETY RAILING INSTALLED


3. ELEVATED CONCRETE FLOORPLATE

7. CONCRETE ROOF PLATE


4. MODULES INSTALLED
8. WINDOWS AND BRISE SOLEIL INSTALLED
10. COMPLETION AND USE